Archives: August 2021

Unit Two Lower Level Walls Formed and Poured


Unit Two Footings Poured

10# reinforced concrete footings.


Unit Two Site Excavation

Unit Two Site Excavation. Dolomite gravel layered in preparation for concrete slab. Structural steel arriving on site in the next ten days.