Construction Updates

Installing Windows and Doors


X Factor Construction Reaches the Summit


Unit Two Master Suite Framing Underway





Unit Two Lower Level Walls Formed and Poured


Unit Two Footings Poured

10# reinforced concrete footings.


Unit Two Site Excavation

Unit Two Site Excavation. Dolomite gravel layered in preparation for concrete slab. Structural steel arriving on site in the next ten days.


July 2021 Project Updates

Much has been accomplished over the winter and spring with demolition, engineering, permitting and planning. Utility and infrastructure work got underway in June. Construction of the first residence on Unit Two commenced in July. Check back often to watch our progress. Three to Four Bedroom Residence Under Construction on Unit Two Unit Number Two Site Excavation – July 9, 2021